Question: Identify the critical path using the two path method. Hint work left to right and then right to left. The critical path is the path
Identify the critical path using the two path method. Hint work left to right and then right to left. The critical path is the path with no slack.
Activity
Precedence
Duration
A
B
A
C
B
D
A
E
D
F
D
G
CEF