Question: Identify the ONE correct statement regarding process group interactions within the management of a project. Group of answer choices Generally speaking, the output of one

Identify the ONE correct statement regarding process group interactions within the management of a project. Group of answer choices Generally speaking, the output of one process becomes the input to another process. The project management process groups are not linked by objectives, but by the project deliverables that the project manager defines. The project planning documents, once written, never change throughout the life cycle of a project. The process groups within a project are discrete events and have no overlap within a project life cycle