Question: Identify the procedures to be planned for safe operations within minimum distances set by Table A of Section 1 4 0 8 from the list
Identify the procedures to be planned for safe operations within minimum distances set by Table A of Section from the list below:
Any reclosing feature of a circuit interrupting device must be made inoperative
Utilize a dedicated spotter in continuous contact with the crane operator
Use an elevated warning line or barricade
Use an insulated link device between the end of the load line and load
Use nonconductive rigging
Set automatic range limiters if crane is so equipped
Use nonconductive tag lines if tag lines are required
Set perimeter barricades at feet from equipment
Prohibit all workers other than the crane operator from touching the load line above the link insulator or touching the crane.
Allow only essential personnel in the area of the crane and load
Properly ground equipment
Install an insulated blanket or cover over the utility line unless voltage prohibits
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock