Question: Identify the statement that is not correct regarding a project budget. Group of answer choices The budget is not an expression of organizational policy. The
Identify the statement that is not correct regarding a project budget.
Group of answer choices
The budget is not an expression of organizational policy.
The budget is included in a project plan.
The budget serves as a control mechanism for the project.
The budget serves as a basis for comparison of planned and actual usage of resources.