Question: IET418 Chapter 4 Practice Problem-1 Given the following information, determine the productive hour cost for each of the machine centers shown. Assume that the direct
IET418 Chapter 4 Practice Problem-1 Given the following information, determine the productive hour cost for each of the machine centers shown. Assume that the direct labor budget includes the fringe cost for direct labor. Show calculations of how you arrive at the answer Direct labor Direct labor Hours 1600 640 320 Machine center Fabrication Area (S 25000 6000 1900 Depreclation 27000 200 1800 Testi Hrs 2200 325 650 1000 500 4000 20165 12296 8744 Test OHS Plant s Indirect Utilities Indirect Labor Amount (S Allocation Basis Area Direct Labor Hours HP-Hours Direct Labor Hours Direct Labor Hours Direct Labor Hours es16000 4200 4000 13000 3000 Administration