Question: If A , B , and C are three activities connected with SS and FF ( combination ) relationships with 2 - day lag on

If A, B, and C are three activities connected with SS and FF (combination) relationships with 2-day lag on the SS relationships only. Their durations are 5, 10, and 3; respectively. The duration of the project is days.