Question: If a company is working under a certain lead time schedule what is the reorder point for the following information? a. Lead Time =13 hours

If a company is working under a certain lead time schedule what is the reorder point for the following information? a. Lead Time =13 hours b. Demand =30 per hour RE=390 hours What would the new reorde