Question: If a company undertakes a quality improvement program, it would spend an additional $370,000 on raw materials inspection and an additional $250,000 on finish
If a company undertakes a quality improvement program, it would spend an additional $370,000 on raw materials inspection and an additional $250,000 on finish goods inspection. This quality improvement program would save the company $410,000 in rework. What would be the cost or savings of undertaking this quality improvement program? OA. $1,030,000 in additional costs OB. $210,000 in additional costs OC. $210,000 in savings OD. $1,030,000 in savings