Question: If a delay in an activity will not delay completion of the whole project, the activity _________. Group of answer choices has a short expected
If a delay in an activity will not delay completion of the whole project, the activity _________.
Group of answer choices
has a short expected completion time
has slack
is one of the first tasks to be completed
has a long expected completion time
is on the critical path
In making a backward pass through a network, activity L has an activity time of 6 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 32, 27, and 26, respectively. The late finish times for activities M, P, and T are 39, 37, and 33, respectively. What is the late start time for activity L?
Group of answer choices
20
22
13
33
17