Question: If a load report ( resource requirements profile ) shows a work center scheduled beyond capacity: Group of answer choices the work center's load may
If a load report resource requirements profile shows a work center scheduled beyond capacity:
Group of answer choices
the work center's load may be smoothed by such tactics as operations splitting or lot splitting.
the company must add capacity by such tactics as overtime and subcontracting.
the aggregate plan must be revised.
the WagnerWhitin algorithm should be used to rebalance the load.
the company must add capacity by enlarging the facility.