Question: If a plan estimates that 5,184 labor-hours will be expended on a series of related construction activities, and the projected number of construction worker equivalents
If a plan estimates that 5,184 labor-hours will be expended on a series of related construction activities, and the projected number of construction worker equivalents expected to perform that activity is 12 personnel working a 12-hour day, what is the calculated overall duration for those activities? Assume the work is performed sequentially