Question: If a production team experiencing a 75% learning rate takes 10 hours to produce the 4th unit, how many hours would it be expected to

If a production team experiencing a 75% learning rate takes 10 hours to produce the 4th unit, how many hours would it be expected to take to produce the 12th unit? Hint: find the time for the first unit that causes the 4th unit to be 10 hours. Once you now T(1), you can then find T(12). I used the excel template example and and kept plugging numbers until I found it. Time for unit 1 is between 10 and 20. Question 4 options:

6.4

4.8

13.5

10.1