Question: If a project has a negative net present value, the internal rate of return will be A) less than the discount rate. B) greater than
| If a project has a negative net present value, the internal rate of return will be | |
| A) | less than the discount rate. |
| B) | greater than the discount rate. |
| C) | equal to the discount rate. |
| D) | a negative rate of return. |