Question: If a project has a net present value equal to zero, then: Question 30 options: IRR must also equal zero. The IRR is larger than
If a project has a net present value equal to zero, then:
Question 30 options:
|
|
IRR must also equal zero.
|
|
|
The IRR is larger than the required rate of return.
|
|
|
A decrease in the project's initial cost will cause the project to have a negative NPV.
|
|
|
Any delay in receiving the projected cash inflows will cause the project to have a positive NPV.
|
|
|
The present value of all cash inflows must equal the costs of the project. The IRR is equal to the required rate of return.
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
