Question: If a project has an expected (average) completion time of 15 and standard deviation of 1.70, what due date should the team set if they

If a project has an expected (average) completion

If a project has an expected (average) completion time of 15 and standard deviation of 1.70, what due date should the team set if they want to be 99% sure that they will complete the project on time? Note: Only round your final answer to 2 decimal places. Your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock