Question: If a project has exactly one critical path, which one of the following statements is TRUE? Crashing an activity on the critical path will always
If a project has exactly one critical path, which one of the following statements is TRUE?
- Crashing an activity on the critical path will always result in an increase in total project profits.
- Crashing activities on the critical path will always result in having multiple critical paths for the project.
- Crashing an activity on the critical path will always result in a reduced total project completion time.
- The best schedule is one in which all activities are crashed as much as possible.
- All of the above
- None of the above