Question: If a project includes two tasks. Install wiring and inspect electrical system, and inspect electrical systems cant finish until install wiring finishes what type of
If a project includes two tasks. Install wiring and inspect electrical system, and inspect electrical systems cant finish until install wiring finishes what type of time dependency exists between these activities?
- Finish-to-start (FS)
- Finish-to-finish (FF)
- Start-to-start (SS)
- Start-to-Finish (SF)