Question: If a project's actual costs and earned value are under the planned value, then we can assume the project is over budget and ahead of

If a project's actual costs and earned value are under the planned value, then we can assume the project is over budget and ahead of schedule the project is under budget and ahead of schedule the project is over budget and behind schedule the project is under budget and behind schedule