Question: If a task in a given project has a critically index of 0 . 1 5 , what does this number say about that task?

If a task in a given project has a critically index of 0.15, what does this number say about that task?
Group of answer choices
This task is more critical than 15% of the other tasks in the project
This task occurs before 85% of the other tasks on the critical path
The duration of that task is likely to be 15% of the overall duration of the project
This task has a 15% probability of being on the critical path of a project