Question: If activity A were to be delayed and takes three days longer than planned, by how much would the project be delayed? What will happen

If activity A were to be delayed and takes three days longer than planned, by how much
would the project be delayed? What will happen to the critical path? Your answer should
be in terms of the following.
i. The project completion time will be 24 months, the critical path will remain the
same.
ii. The project completion time will be 21, the critical path will remain the same.
iii. The project completion time will be 24, there will be an alternative critical path
in addition to the current critical path.
iv. The project completion time will be 18, critical path will remain the same

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!