Question: If activity I is delayed by four days, the project duration will be delayed by four days. False True If activity G is delayed by
If activity I is delayed by four days, the project duration will be delayed by four days.
False
True
If activity is delayed by two days, the project duration will be delayed.
False
True
If activity is delayed by two days, the early start of activity will be delayed.
True
False
If activity is delayed by six days, the project duration will be delayed.
False
True
If activity is delayed by six days, the early start of activity I will be delayed.
True
False
If the duration of I is days instead of five days, select all critical paths.
ABFIL
ABDGKL
ABEKL
ABDHKL
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
