Question: If all risks in the table below occurred during project life, how many days will the project below be delayed, considering all affected activities are

If all risks in the table below occurred during project life, how many days will the project below be delayed, considering all affected activities are on the project critical path?
Risk
Probability
Impact
Effect
A
20%
30 Days
Delay
B
10%
20 Days
Delay
C
30%
10 Days
Delay
D
15%
20 Days
Saving
40 days
80 days
8 days
60 days