Question: If an activity can be completed in 10 weeks at a cost of $3800 instead of the normal time of 13 weeks at a cost

If an activity can be completed in 10 weeks at a
If an activity can be completed in 10 weeks at a cost of $3800 instead of the normal time of 13 weeks at a cost of $2400, then the crash cost per week for the given activity is ......... (Closest whole number) We