Question: If an activity conducted by a KPU proof-reader (reading reports for payment) whose normal duration is 55 days can be shortened to 50 days for

  1. If an activity conducted by a KPU proof-reader (reading reports for payment) whose normal duration is 55 days can be shortened to 50 days for an added cost of $4,5000, the crash cost per day is:

A) $900.

B) $500.

C) $9,000.

D) $4,500.

E) $90. show work