Question: If an end good has a one - week lead time and a customer requires the order to be ready in Week 7 , when

If an end good has a one-week lead time and a
customer requires the order to be ready in
Week 7, when should the key components (lead
time =3 weeks) be ordered?
A. Week 1 B. Week 3 C. Week 6 D. Week 7