Question: If an owner needs to complete a project in the least time possible because of an emergency, he or she may use a conceptual cost
If an owner needs to complete a project in the least time possible because of an emergency, he or she may use a conceptual cost estimate
a to postpone the work
b as part of a negotiated contract
c to subcontract work through addenda
d as a final price