Question: If annual demand is 5 0 , 0 0 0 units and the purchase order lead - time is 4 weeks, what is the reorder

If annual demand is 50,000 units and the purchase order lead-time is 4 weeks, what is the reorder point?
Answer
1,924 units
3,125 units
12,500 units
3,848 units
I don't know yet

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock