Question: If any material or portion of the work does not conform to the requirements, the inspector should _ _ _ _ _ _ _ _

If any material or portion of the work does not conform to the requirements, the inspector should ___________________________.
record it in the daily log only
stop work and call the owner
notify the contractor, explain why it does not conform, and record it in the daily diary
stop work, notify the architect/engineer, and record it in the daily diary