If CPI = 1.1 and SPI = 0.95, then the trend for the project is: running under
Fantastic news! We've Found the answer you've been seeking!
Question:
If CPI = 1.1 and SPI = 0.95, then the trend for the project is: running under budget but behind schedule. discuss expand and explain.