If : GE---5103-2D1-SP-2023[Based on Project Management Professional (PMP) Based on PMBOK7]
Of the following, which represent the purpose of creating the project charter? (Choose two.)
Officially authorizes the project to begin
B
Documents the baseline budget for the project
C
Creates the detailed scope of the project
D
Ensures stakeholders have a clear and common understanding of the project
Details the deliverables and timelines of the project