Question: If General Foundry will save $2000 for each week that the earliest completion time is reduced, which single option, if any, should Lester choose? And

If General Foundry will save $2000 for each week that the earliest completion time is reduced, which single option, if any, should Lester choose? And why? 2. Ttee following table renresents a nlan for a nroiect: a. Construct the appropriate network diagram. b. What is the critical path? c. What is the expected completion time for the project and what is the variance of project completion time? e. Is the probability that the project will take less than 20 days to complete larger than 50% or smaller than 50% ? And why