Question: If it appears that meeting the project's cost - schedule - scope equilibrum will compromise the original business objective, what's the project manager's FIRST course

If it appears that meeting the project's cost-schedule-scope equilibrum will compromise the original business objective, what's the project manager's FIRST course of action?
A) Set realistic expectations
B) Gain acceptance from aff stakeholders
C) Reevaluate the project target
D) Connect to the business case
 If it appears that meeting the project's cost-schedule-scope equilibrum will compromise