Question: If one project has a higher standard deviation than another, Group of answer choices it may have a lower expected value. it may have a

If one project has a higher standard deviation than another,

Group of answer choices

it may have a lower expected value.

it may have a lower risk.

it has fewer possible outcomes.

it may be riskier, but this can only be determined by the coefficient of variation.