Question: If one resource is assigned to a task with a duration of 1 day, the total work would be ____. Question 34 options: 8 hours
If one resource is assigned to a task with a duration of 1 day, the total work would be ____. Question 34 options: 8 hours 1/7 week 1/30 month Any of the above
Step by Step Solution
There are 3 Steps involved in it