Question: If project 1 ?is selected, projects 5 ?or 6 ?must be selected. Question 3 5 ?options: X 1 + ?X 5 + ?X 6 >

If project 1 ?is selected, projects 5 ?or 6 ?must be selected.
Question 3 5 ?options:
X 1 + ?X 5 + ?X 6 > = 2
X 1 < = ?X 5 + ?X 6
X 1 < ?X 5 + ?X 6
X 1 > ?X 5 + ?X 6
X 1 < = ?X 5 , ?X 1 < = ?X 6
X 1 + ?X 5 + ?X 6 > = 1
X 1 > = ?X 5 + ?X 6
X 1 = ?X 5 + ?X 6