Question: If Project A's IRR exceeds Project B's, then A must also have the higher NPV.. If the NPV is negative, the IRR must also be
If Project A's IRR exceeds Project B's, then A must also have the higher NPV.. If the NPV is negative, the IRR must also be negative. If a project with normal cash flows has an IRR less than the WACC, the project must have a positive NPV. If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV. Which method of evaluating capital projects is best for making the accept/reject decision for independent projects? Select one MIRR All three methods (NPV, IRR, and MIRR) ate equally good for evaluating independent projects because they will always reach the same accept/reject conclusion. NPV. IRR
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
