Question: If the backward pass through a network works backward from the earliest calculated finish time for the entire project, then all activities on the critical
If the backward pass through a network works backward from the earliest calculated finish time for the entire project, then all activities on the critical path will: Group of answer choices have slack time that is impossible to predict have positive slack time have negative slack time have zero slack time