Question: If the budget at completion for a project is $200,000 and the cost performance index is .5, wh estimate at completion? $100,000$300,000$400,000$180,000 1 point Quantitative

If the budget at completion for a project is
If the budget at completion for a project is $200,000 and the cost performance index is .5, wh estimate at completion? $100,000$300,000$400,000$180,000 1 point Quantitative risk analysis should only be performed on risks with higher qualitative risk exposure. True False 1 point You need to plan the project scope and determine what activities need to be done before you can develop a detailed project schedule.. True False