Question: If the cash flows for project A are C0 = -3,000, C1 = +500; C2 = +1,500; and C3 = +5,000, calculate the NPV of

If the cash flows for project A are C0 = -3,000, C1 = +500; C2 = +1,500; and C3 = +5,000, calculate the NPV of the project using a 15 percent discount rate.