Question: If the Earned Value Management ( EVM ) data for Project B is as follows: Latest Revised Estimate ( LRE ) = 9 , 5

If the Earned Value Management (EVM) data for Project B is as follows:
Latest Revised Estimate (LRE)=9,500
Actual Cost of Work Performed (ACWP)=3,800
Budget At Completion (BAC)=6,445
Budgeted Cost of Work Performed (BCWP)=3,300
Budgeted Cost of Work Scheduled (BCWS)=4,250
Then a Three-Point Estimate for Project B would be:
Minimum =6,445
Most Likely (Point)=8,022
Maximum =8,864
Minimum =6,445
Most Likely (Point)=7,922
Maximum =8,964
Minimum =4,250
Most Likely (Point)=6,422
Maximum =6,950
Minimum =6,445
Most Likely (Point)=7,422
Maximum =8,464
Minimum =4,250
Most Likely (Point)=7,422
Maximum =8,464

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!