Question: If the expected completion time of a project is 35 days, what is the probability that the project takes longer than 38 days? The standard
If the expected completion time of a project is 35 days, what is the probability that the project takes longer than 38 days? The standard deviation of the critical path is 6 days. (input a number between 0 and 1 rounded to two decimal places)