Question: If the Initial quote for this project is 20 weeks at a cost of $15,000. What is the total cost (original + crash costs) to

If the Initial quote for this project is 20 weeks at a cost of $15,000. What is the total cost (original + crash costs) to crash it by 3 weeks?

Activity

Immediate Predecessors

Duration

# of Weeks Activity can be Crashed

Direct Cost Per Week

A

-

5

1

$800

B

-

4

1

$300

C

A, B

3

-

-

D

C

2

1

$375

E

C

2

1

$400

F

E

5

2

$2000

G

D, F

5

1

$1000

Group of answer choices

$17,200

$17,500

$17,800

$18,200