Question: If the Initial quote for this project is 20 weeks at a cost of $15,000. What is the total cost (original + crash costs) to
If the Initial quote for this project is 20 weeks at a cost of $15,000. What is the total cost (original + crash costs) to crash it by 3 weeks?
| Activity | Immediate Predecessors | Duration | # of Weeks Activity can be Crashed | Direct Cost Per Week |
| A | - | 5 | 1 | $800 |
| B | - | 4 | 1 | $300 |
| C | A, B | 3 | - | - |
| D | C | 2 | 1 | $375 |
| E | C | 2 | 1 | $400 |
| F | E | 5 | 2 | $2000 |
| G | D, F | 5 | 1 | $1000 |
Group of answer choices
$17,200
$17,500
$17,800
$18,200
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts