Question: If the net present value of a project is zero based on a discount rate of 16%, then the internal rate of return is: If

If the net present value of a project is zero based on a discount rate of 16%, then the internal rate of return is:

If the net present value of a project is zero based on

If the net present value of a project is zero based on a discount rate of 16%, then the internal rate of return is: Multiple Choice equal to 16%. less than 16% o greater than 16%. cannot be determined from this data