Question: If the NPV for a project is < 0, it indicates that the project will ________. A. Report a profit loss B. Report a profit
If the NPV for a project is < 0, it indicates that the project will ________.
| A. | Report a profit loss | |
| B. | Report a profit gain | |
| C. | Fail to cover its required rate of return | |
| D. | Fail to generate cash inflows |