Question: If the optimistic estimate is 1 , the pessimistic estimate is 9 , and the most likely estimate is 8 , what is the PERT
If the optimistic estimate is the pessimistic estimate is and the most likely estimate is what is the PERT estimate?
Group of answer choices
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock