Question: if the program is on the DOT&E oversight list, which one of the following test and evaluation (T&E) products is required before the full rate
if the program is on the DOT&E oversight list, which one of the following test and evaluation (T&E) products is required before the full rate production decision review.
A. LPIR Article quantities approval
b. early operational assessment
c. live fire T&E waiver
d. DOT&E report on initial operational test and evaluation (IOT&E)