Question: If the project team is using the Critical Chain scheduling method to account for constrained resources, what types of buffers can the team use to

If the project team is using the Critical Chain scheduling method to account for constrained resources, what types of buffers can the team use to address the constraints?
Feeding Buffers
Project Buffers
Float
Both a and b