Question: If the Reliability Coordinator identifies an IROL for a future operating day due to scheduled outages, they are required to do which of the following?

If the Reliability Coordinator identifies an IROL for a future operating day due to scheduled outages, they are required to do which of the following? Cancel all outages for the operating day Develop a mitigation plan Declare an EEA 3 for the hours of concern Review its restoration plan