Question: If the schedule variance for a project is negative, and the cost performance index is positive, then we can say the project has which of
If the schedule variance for a project is negative, and the cost performance index is positive, then we can say the project has which of the following status?
Group of answer choices
Ahead of schedule, over budget
Behind schedule, under budget
Ahead of schedule, under budget
Behind schedule, over budget