Question: If the schedule variance for a project is negative, and the cost performance index is positive, then we can say the project has which of

If the schedule variance for a project is negative, and the cost performance index is positive, then we can say the project has which of the following status?

Group of answer choices

Ahead of schedule, over budget

Behind schedule, under budget

Ahead of schedule, under budget

Behind schedule, over budget