IF the tasks in a WBS do not include the tasks implied by the scope statement, then
Fantastic news! We've Found the answer you've been seeking!
Question:
IF the tasks in a WBS do not include the tasks implied by the scope statement, then the WBS is not complete.
Review Later
True
False